Panther Island timeline.

Key dates for the Panther Island and Central City flood-control project in Fort Worth, with a link to the source for each one. Plans and schedules change, so check official sources.

2006

The first formal vision plan for the land is developed. Source: Urban Land

2022

The Army Corps moves toward separate contracts for the north and south channels, flood-proofing, the pump station and dams. Source: Fort Worth Report

2022

Encore Panther Island, a 300-unit apartment community at Fourth and North Main, opens as the first multifamily project on the Panther Island riverwalk. Source: NBC DFW

Early 2023

$403 million in federal money is announced for the final design and construction of the bypass channel. Source: Dallas Innovates

March 2024

Vision 2.0 is presented: a framework for a mixed-use waterfront district on about 190 developable acres. Source: HR&A Advisors

January 2025

The project, estimated at about $1.16 billion, is still reported on track for 2032 despite delays. Source: Fort Worth Report

June 2025

Federal construction disputes push the flood-control work back again. Source: Fort Worth Report

Nov. 5, 2025

The Tarrant Regional Water District issues a Request for Qualifications to find development partners for the first phase of the 300-plus-acre Panther Island district. Source: TRWD

Nov. 2025

TRWD says it will begin building the next section of the Panther Island canal system in mid-2026, to set up future development on the island. Source: TRWD

September 2026

A $169 million contract is reported awarded for the north bypass channel, with construction expected to start this winter or in early 2027. Source: Yahoo News

Oct. 14, 2026

David films excavation work on Panther Island from the air. What the video shows is his firsthand view; official sources had not confirmed this section of canal work when it was filmed.

Oct. 22, 2026

Public open house on the Central City project at Northside Community Center, 6 to 7:30 p.m. Source: City of Fort Worth

June 2027 (scheduled)

The City says bridge construction follows once the Tarrant Regional Water District finishes Canal C, which is scheduled for June 2027. Source: City of Fort Worth

2032 (target)

The overall completion target for the flood-control project has been 2032. Dates have moved before and may move again. Source: Fort Worth Report